22h54 on 17/4, at the 500kV Vinh Tan substation (TBA) (Tuy Phong district, Binh Thuan), the Southern Power Project Management Board (SPMB) coordinated with related units to organize successfully energized AT1 500kV – 900MVA transformer (MBA).
The project is ready to collect renewable energy sources in the region to transfer capacity to the national electricity transmission grid, making an important contribution to ensuring electricity supply to the southern central and regional provinces. South. Also avoid overloading the existing 500/220 kV-600 MVA transformers of the Vinh Tan 500kV TBA.
Vinh Tan 500kV TBA capacity increase project is divided into 3 phases, SPMB has completed phase 1 of transformer AT1 500kV-900MVA and related equipment. Immediately after energizing the AT1 MBA at Vinh Tan 500kV substation, it brought 177MW.
Phase 2, SPMB continues to deploy in June 2020 with installation items of AT2 MBA 500kV – 900MVA. Phase 3, SPMB will be implemented in October 2020 with items to install equipment of 220kV highways and compartment transfer.
Mr. Truong Huu Thanh – Secretary of the Party Committee, Director of SPMB said: To complete the assigned tasks, the Party Committee and SPMB leaders have gathered all resources and direction, together with the units participating in the project. have adequate facilities and manpower to both ensure the prevention of C0VID-19 epidemic diseases, and deploy the investment and construction of projects to ensure quality, technical requirements, fine arts and safety for laborers. dynamic.
Paragraph
Mr. Truong Huu Thanh added: The completion of phase 1 is 12 days ahead of schedule in accordance with the adjusted plan and more than 2 months in line with the plan assigned by EVNNPT in 2020, practically welcoming the 1st EVNNPT Party Committee. III, term 2020 – 2025 towards the Party Congress of Vietnam Electricity and the 13th National Party Congress.